Enterprise Products, Enbridge Announce Completion Of Seaway Pipeline Reversal

http://fbcoem.files.wordpress.com/2012/05/web_seawayprojectmap_12-28-111.jpg

(RTTNews.com) – Enterprise Products Partners L.P. (EPD) and Enbridge Inc. (ENB, ENB.TO) said Thursday that modifications to the Seaway crude oil pipeline allowing it to transport crude oil from Cushing, Oklahoma to the U.S. Gulf Coast have been completed.

According to the companies, the pipeline is in the process of being commissioned, and the first flows of crude oil into the line are expected to begin this weekend.

The reversal of the 500-mile, 30-inch diameter pipeline, which had been in northbound service since 1995, provides North American producers with the infrastructure needed to access more than 4 million barrels per day of Gulf Coast refinery demand.

The reversal will initially provide 150,000 BPD of capacity, which is expected to increase to more than 400,000 BPD in the first quarter 2013 with additional modifications and increased pumping capabilities.

Seaway Crude Pipeline Company LLC is a 50/50 joint venture owned by affiliates of Enterprise Products Partners and Enbridge Inc. In addition to the pipeline that transports crude oil from Cushing to the Gulf Coast, the Seaway system is comprised of a terminal and distribution network originating in Texas City.

For comments and feedback: contact editorial@rttnews.com

http://www.rttnews.com

Source

Advertisements

Enbridge, Enterprise Products To Reverse Seaway Crude Oil Pipeline

image

(RTTNews) – Enbridge Inc. (ENB.TO: News ,ENB: News ) and Enterprise Products Partners L.P. (EPD: News ) agreed to reverse the direction of crude oil flows on the Seaway pipeline to enable it to transport oil from Cushing, Oklahoma to the U.S. Gulf Coast. Pending regulatory approval, the line could operate in reversed service with an initial capacity of 150,000 barrels per day by second quarter 2012.

Patrick Daniel, President and Chief Executive, Enbridge Inc., said, “A Seaway reversal will provide capacity to move secure, reliable supply to Texas Gulf Coast refineries, offsetting supplies of imported crude.”

Meanwhile, Michael Creel, President and Chief Executive of Enterprise’s general partner, noted, “We believe that reversing the direction of crude oil movement on Seaway and the construction of additional infrastructure will accelerate access to Gulf Coast markets, reduce transportation costs, improve both producer and refiner economics and hasten the development of North America’s crude oil reserves.”

Following pump station additions and modifications, anticipated to be completed by early 2013, the capacity of the reversed Seaway Pipeline would be up to 400,000 barrels per day in mixed service, the company noted. Enbridge and Enterprise anticipate that the reversed Seaway pipeline would be fully contracted. After reversing the direction that crude oil flows on the 500-mile, 30-inch diameter, long-haul pipeline, Seaway would deliver crude from Cushing into the Houston-area market by utilizing existing affiliate and third-party pipelines as well as its Texas City local pipeline system.

Source