Seaway – Echo terminal link planned

image

News wires  02 March 2012 02:57 GMT

The proposed pipeline would be about 40 miles long, Enbridge executive Brad Shamla told Reuters.

“We are shipping crude out over a dock to other destinations on the Gulf Coast,” he said.

Following this, another pipeline would be laid, this one from the Echo terminal, along the Houston Ship Channel, to the Port Arthur area of Texas on the border of Louisiana.

Shamla said that pipeline will be about 80 miles in length and be done in 2014.

The plan was announced as the companies continued their purging of the 500-mile Seaway pipeline, which they said was ahead of schedule.

The pipeline will begin by carrying 150,000 barrels per day by 1 June from the oil hub of Cushing, Oklahoma, to Gulf Coast refineries, said Shamla.

The pipeline is the first of several projects to siphon the glut of crude oil sitting in Cushing to the refineries along the Gulf Coast.

The reversed Seaway pipeline capacity is expected to grow 400,000 bpd in 2014 but could increase more if the current open season seeking more firm shipping commitments is successful, Reuters reported.