Corpus Christi, TX: Tamar Platform En Route to Israel

Tamar production platform has left the Keiwit Shipyards in Corpus Christi, Texas, USA, and is now on the way to its location offshore Israel, according to Globes, the Israeli financial newspaper.

It took 18 months for the 280 m platform to be completed, and the project has been described as “the largest infrastructure project in Israeli history.”

Noble Energy, operator of the Tamar field, did not immediately respond to an e-mail seeking comment.

The Tamar platform will be located in approximately 800 feet of water and will be able to process 1.2 billion standard cubic feet of gas per day. The Tamar field is estimated to contain 8.4 trillion cubic feet of gas and will be produced through several subsea wells connected to the platform by 150 km long flow lines. The single-lift topsides facility has four deck levels and weighs nearly 10,000 tons.

Globes further reports that the platform is expected to reach its destination during the fourth quarter this year. First production is scheduled for March 2013.

Noble Energy operates Tamar with a 36 percent working interest. Other owners are Isramco Negev 2 with 28.75 percent, Delek Drilling with 15.625 percent, Avner Oil Exploration with 15.625 percent, and Dor Gas Exploration with the remaining four percent.

Tamar Platform En Route to Israel| Offshore Energy Today.

Israel: Pinnacles Delivers First Gas

Israel’s  Delek Group has been informed by the operator, Noble Energy Mediterranean Ltd., that on June 12, 2012, development of Pinnacles #1 was completed and gas began to flow from it.

Pinnacles offshore well was recently linked by a subsea pipeline to the nearby Mari B production platform. Helix ESG’s reeled pipelay vessel, Express, which in April arrived at the port city of Haifa, Israel, completed the SURF (Subsea Umbilicals, Risers and Flowlines) work.

According to the Israel-based financial newspaper The Globes, Pinnacles well will produce 150 million cubic feet of gas per day.

Noble Energy Mediterranean Vice President Lawson Freeman told The Globes that the company was excited to bring the Pinnacles well on stream. He also added that the company was pushing hard to accelerate the Noa development in the same way.

Development of the Noa field is geared to allow for additional supplies of natural gas to the Israeli market, until the start of natural gas supplies from the Tamar project in early 2013.

Source

Noble Energy Linking Noa and Pinnacles to Mari B Platform

https://i1.wp.com/d3n6f555sx1wcx.cloudfront.net/wp-content/uploads/2012/05/Noble-Energy-Linking-Noa-and-Pinnacles-to-Mari-B-Platform.jpg

Noble Energy and Delek Group have started linking Noa and Pinnacles offshore natural gas fields to the Mari B production platform, according to the Israel’s financial newspaper Globes.

Helix ESG’s reeled pipelay vessel, Express, which in April arrived at the port city of Haifa, Israel has started SURF (Subsea Umbilicals, Risers and Flowlines) work.

According to the data on Noble Energy’s website, Noa will, once developed, provide 100 million cubic feet per day (MMcf/d) of production by September 2012.

Development of the Noa field is geared to allow for additional supplies of natural gas to the Israeli market, until the start of natural gas supplies from the Tamar project.