Enhanced recovery through subsea compression at Gullfaks

Statoil and partner Petoro have agreed to apply subsea gas compression on the Gullfaks South field. This technological leap forward represents an important milestone in the efforts to improve recovery from this and other gas fields.

This technology adds 22 million barrels of oil equivalent to the production from the Gullfaks South Brent reservoir. The partners will invest some NOK three billion in the technology project scheduled to be completed in the autumn of 2015.

“Innovation and technology development are essential to improved oil and gas recovery and extended life for the fields on the Norwegian continental shelf. The development of subsea compression and processing is a central part of Statoil’s technology strategy for long-term production growth,” says Statoil’s executive vice president for Technology, Projects and Drilling, Margareth Øvrum.

The Gullfaks project is the second large subsea gas compression project planned by Statoil. In April this year the plan for development and operation for Åsgard subsea compression was approved by the Norwegian Parliament.

Both projects are scheduled to be compled in 2015. Furthermore Statoil is responsible for the technology qualification for Shell for a third not yet decided project, the Ormen Lange pilot. There are good synergies between the different projects.

Subsea gas compression is an important step on the road towards Statoil’s ambition of installing the elements for a ”subsea factory”. Subsea processing is key to getting access to resources in Artic areas and deepwater assets.

Read more:  Enhanced recovery through subsea compression at Gullfaks.